Replacement of all AHUs and Ventilation Fans serving Operating Theatres 6 & 7.
Demolition of all existing redundant services.
Replacement of Operating Theatre ductwork and Laminar Flow Hoods.
Provide all Mechanical Electrical services and integration of new services to existing Building Management System.
Temporary HEPA filtered exhaust systems to prevent dust egress from construction and maintain required Operating Theatre Suite pressure gradients.
Detailed work methodologies were generated for all project phases through close collaboration with the client’s team to ensure no impact on day-to-day operations.
Zero Lost Time Injuries or Near Misses for the project duration.
Zero unplanned service interruptions to Hospital Operating Theatre outside of construction zone.
Complete all commissioning and validation of Operating Theatres using inhouse Commissioning Department;
Compliance with all finalisation procedures and handover documentation.
All works were completed safely and on schedule to the expected quality requirements.
Special commendation from LARU inspections team at quality of the project -ZERO defects at certification.