Cottesloe Central – Central Plant





AboutThe Client



Replacement of major Central Plant equipment – Chiller and associated components to operational retail shopping centre.

Provide all upgrades to Mechanical Electrical services and the Building Management System.

Completion of all plant and service commissioning and integration with in-house Commissioning Department.

Comprehensive training and handover procedure with client facility engineering team training.



Project Details

  • Location: Cottesloe, WA
  • Construction Value: $ 0.4M
  • Client: Primewest
  • Managing Contractor: Primewest
cottesloe central central plant3
cottesloe central central plant2
cottesloe central central plant

Delivery

Overall management and delivery of all works.

  • All key program milestone dates achieved.
  • Zero unplanned service interruptions.
  • Zero LTIs or Near Misses.

Comprehensive methodologies developed for each phase of project;

  • Existing plant decommissioning.
  • Crane operations, traffic management and local authority permits.
  • New plant installation and connection with no client service interruption.
  • New plant and service integration into existing systems.

Provide all upgrades to Mechanical Electrical services and the Building Management System.

Completion of all plant and service commissioning and integration with in-house Commissioning Department.

Comprehensive training and handover procedure with client facility engineering team training.