The Curtin University Midland project was a new build $22 million 3-storey campus, for which Centigrade provided all the Mechanical services. The works included the supply and install of 2-off Air-Cooled Chillers and 2-off Heating Water boilers located within the level 3 Plant Room, inclusive of HtgW and ChW Pipework. The supply and installation of various VAV Air Handling Units serving all levels, inclusive of fans, exhaust fans, attenuators, VAV boxes, ductwork and diffusion.
The biggest challenge that we overcame was the setting out of the level 3 Plant Room which had a huge amount of plant that consisted of 2 Chillers, 2 Boilers, 6 AHU’s and dozens of fans (exhaust and supply air), chilled and heating water storage tanks and pumps. None the less, the project was completed on time and within budget and was opened in November 2019.